Definitions
The following definitions (as per the SAMREC Code 2009)
have been applied in estimation and categorisation of the
mineral resources and mineral reserves disclosed within
this document.
Mineral Resource:
Is a concentration or occurrence of material of economic
interest in or on the earth’s crust in such form, quality and
quantity that there are reasonable and realistic prospects
for eventual economic extraction. The location, quantity,
grade, continuity and other geological characteristics
of a Mineral Resource are known, or estimated from
specific geological evidence, sampling and knowledge
interpreted from an appropriately constrained and
portrayed geological model. Mineral Resources are subdivided,
and must be so reported, in order of increasing
confidence in respect of geoscientific evidence, into
Inferred, Indicated and Measured categories.
A deposit is a concentration (or occurrence) of material
of possible economic interest, in or on the earth‘s crust,
that may include mineralised material that cannot be
estimated with sufficient confidence to be classified in the
Inferred category. Portions of a deposit that do not have
reasonable and realistic prospects for eventual economic
extraction are not included in a Mineral Resource.
Inferred Mineral Resource:
Is that part of a Mineral Resource for which volume or
tonnage, grade and mineral content can be estimated with
only a low level of confidence. It is inferred from geological
evidence and sampled and assumed but not verified
geologically or through analysis of grade continuity. It
is based on information gathered through appropriate
techniques from locations such as outcrops, trenches, pits,
workings and drill holes that may be limited in scope or of
uncertain quality and reliability.
Indicated Mineral Resource:
Is that part of a Mineral Resource for which tonnage,
densities, shape, physical characteristics, grade and
mineral content can be estimated with a reasonable level
of confidence. It is based on information from exploration,
sampling and testing of material gathered from locations
such as outcrops, trenches, pits, workings and drill holes.
The locations are too widely or inappropriately spaced
to confirm geological or grade continuity but are spaced
closely enough for continuity to be assumed.
Measured Mineral Resource:
Is that part of a Mineral Resource for which tonnage,
densities, shape, physical characteristics, grade and
mineral content can be estimated with a high level of
confidence. It is based on detailed and reliable information
from exploration, sampling and testing of material from
locations such as outcrops, trenches, pits, workings and
drill holes. The locations are spaced closely enough to
confirm geological and grade continuity.
Mineral Reserve:
The economically mineable material derived from
a Measured or Indicated Mineral Resource or both.
It includes diluting and contaminating materials and allows
for losses that are expected to occur when the material
is mined. Appropriate assessments to a minimum of a
pre-feasibility study for a project and a life of mine plan
for an operation must have been completed, including
consideration of, and modification by, realistically
assumed mining, metallurgical, economic, marketing,
legal, environmental, social and governmental factors
(the modifying factors). Such modifying factors must
be disclosed.
Probable Mineral Reserve:
Is the economically mineable material derived from a
Measured or Indicated Mineral Resource or both. It is
estimated with a lower level of confidence than a Proved
Mineral Reserve. It includes diluting and contaminating
materials and allows for losses that are expected to occur
when the material is mined. Appropriate assessments
to a minimum of a pre-feasibility study for a project or a
life of mine plan for an operation must have been carried
out, including consideration of, and modification by,
realistically assumed mining, metallurgical, economic,
marketing, legal, environmental, social and governmental
factors. Such modifying factors must be disclosed.
Proved Mineral Reserve:
Is the economically mineable material derived from a
Measured Mineral Resource. It is estimated with a high
level of confidence. It includes diluting and contaminating
materials and allows for losses that are expected to occur
when the material is mined. Appropriate assessments
to a minimum of a pre-feasibility study for a project or a
life of mine plan for an operation must have been carried
out, including consideration of, and modification by,
realistically assumed mining, metallurgical, economic,
marketing, legal, environmental, social and governmental
factors. Such modifying factors must be disclosed.
| Figure 1: Location of the Venture’s operations |
 |
| |
Brief description of exploration activities
The Venture’s exploration activities aim to increase
geological knowledge and confidence in its mineral
resource base and to comply with legislative
requirements. Exploration is done on two fronts;
exploration is done ahead of operations in current mining
areas to support the mining activities, whilst project
areas are explored to define and quantify new resources.
Exploration is done on an annual basis, primarily through
the drilling of vertical exploration drillholes. Geophysical
surveys (mainly airborne magnetic surveys) have been
conducted on all major operating mines and projects.
The bulk of the exploration drillholes are drilled, as far as
possible, on a pre-determined grid whilst further drillholes
are drilled to target geological anomalies and to provide
geological and geotechnical information for mine planning.
A total of R17.404 million was spent on drilling 21 148 metres
of surface exploration drillholes for the Venture operations
and projects in FY2012.
No feasibility studies were conducted during the
reporting period.
Geological setting
The Venture’s chrome ore-bodies occur in the Bushveld
Complex and its silica deposit occurs in the Magaliesberg
Formation of the Transvaal Super Group (Figure 1). Both
these geological occurrences are found in South Africa.
Chrome ore is mined from both underground (mostly)
and opencast workings, while silica is only mined in
opencast workings.
The Bushveld Complex
The two billion year old Bushveld Complex (the Complex)
is the world’s largest known layered igneous intrusion
and covers an area of 65 000km2. The Complex is
host to the majority of the world’s PGM, chromite and
vanadium resources.
The Complex is divided into five compartments; the
Western Limb, the Eastern Limb, the Northern Limb, the
far Western Limb and the Bethal Limb (Figure 1). Merafe
has operations on the Eastern and Western Limbs of the
complex. The Bushveld Complex is divided vertically into
four suites of rocks; the Rooiberg Group, the Rustenburg
Layered Suite, the Rashoop Granophyre Suite and the Lebowa Granite Suite. The mafic Rustenburg Layered Suite
hosts the chromite deposits of the complex in the highly
continuous chromitite layers of the Critical Zone. The
complex reaches a vertical thickness of up to 9 000m.
The Critical Zone contains 14 individually recognisable
chromitite layers with varying thicknesses and grades. The
primary chromitite layers targeted for chromite extraction
are the LG6A and LG6 Chromitite Layers, usually mined
as a package, and the MG1 Chromitite Layer. The LG6
Package consists of the lower LG6 Chromitite Layer
which is separated from the LG6A Chromitite Layer by a
pyroxenite (waste) middling. The MG1 Chromitite Layer
consists of a single chromitite layer, with occasional
discontinuous internal waste partings.
Figure 2: Schematic stratigraphy of the
Rustenburg Layered Suite with special
reference to the chromitite layers.
(illustration not to scale) |
 |
| |
Magaliesberg Formation
The Magaliesberg Formation is made up of a package
of individual layers of shale, quartzite and hornfels,
which form a sub-formation of the Pretoria Group of
the Transvaal Supergroup. The quartzite layers of the
formation were formed by the deposition of sandstone
sediments into the Transvaal Basin around 2.2 billion years ago. The Magaliesberg Formation is a massive sequence
of quartzite and minor hornfels reaching a few hundred
metres in thickness. The quartzites form a prominent
topographical ridge (mountain range) around the rim of
the Bushveld Complex. The Rietvlei deposit occurs along
a prominent quartzite ridge which strikes north-south. The
ore-body dips towards the east at dips varying between
320 – 620. Jointing throughout the formation is fairly
prominent. The quartzite is very pure, with an average
content of SiO2 of over 90%. There are no indications on
surface of major geological disturbances. A major regional
fault (the Rustenburg Fault) is developed to the southeast
of the mine (just off the mine property).
Type of mining and mining activities
The Venture has chrome mining operations along the
Western and Eastern Limbs of the Bushveld Complex.
The operations along the Western Limb of the Bushveld
Complex comprise the Waterval, Kroondal, Boshoek,
Horizon and Wonderkop mines. The LG6 Package at both
Waterval and Kroondal mines is mined underground using
trackless mining methods on a bord-and-pillar layout.
Boshoek Mine is 20km northwest of Rustenburg. The
MG1, LG5 and LG6 Chromitite Layers are being mined in
open pits. Horizon Mine lies just west of the Pilanesberg
Complex. The LG6 Chromitite Layer is currently being
mined at Horizon Mine through underground operations.
Wonderkop Mine, Waterval/Klipfontein and Extension 9
are exploration projects.
Thorncliffe, Magareng and Helena mines are situated
along the southern portion of the Eastern Limb of the
Bushveld Complex. The MG1 Chromitite Layer is being
mined underground using trackless mining methods
on a bord-and-pillar mining layout. De Grooteboom lies
contiguous to and immediately north of Thorncliffe Mine.
The Venture’s silica deposit lies 15km west of Rustenburg.
Rietvlei Silica is an opencast mine. The quartzite is mined
mainly to supply the Venture’s furnaces with silica.
Ore production
The Venture has mined 4.276Mt ROM ore from 1 January
to 31 December 2012 against a budget of 5.036Mt.
The main contributors to the lower than budgeted ROM
tonnage are Waterval, Kroondal, Thorncliffe and Helena
mines. The lower ROM production at Waterval Mine is
mainly due to industrial action and mining operational
issues. Kroondal Mine experienced similar industrial
action. At Helena Mine the main reasons for the lower
production were equipment breakdowns, Section 54
stoppages and mining operational reasons. The 2012
ROM tonnage is higher than the 2011 ROM production of
3.912Mt as production activities at the main production
units have remained more or less the same as the 2011
production year. Waterval, Magareng and Helena mines
are in build-up phases and increasing their production
rates year-on-year.
The estimates in this statement reflect the mineral
resources and mineral reserves as at 31 December 2012.
Legal entitlement
All new order mining rights applications, mining right
conversions, prospecting rights conversions and new
order prospecting rights for all the main operating units,
have been granted and executed by the Department of
Mineral Resources. Certain Section 102 and Section 11
applications under the MPRDA remain in the ordinary
administrative process, and the Venture has little reason
to believe these will not be granted in due course.
In respect of a portion of Horizon Mine (Ruighoek and
Vogelstruisnek), an application to the High Court has
been made by certain surface rights owners at the mine
to review and set aside the conversion of mining rights
granted by the Minister of the Department of Mineral
Resources and to request that the conversion process
start again. This issue has been settled and as the area
concerned does not fall within the anticipated five-year
mining area it will therefore have no impact on short-term
mine production.
Description of the method and assumptions
made to estimate mineral resources and
mineral reserves
Chrome
Raw geological data is validated through various steps and
routines before being compiled into a final database.
The database data is statistically and geostatistically
analysed to determine the inherent characteristics and
variability of the data. The ore-body characteristics that
are analysed are the distribution and variability of the
thickness, SG of the chromitites and the critical grade
elements (Cr2O3, FeOtotal and SiO2). The results of the
geostatistical analysis are used as input parameters for
the creation of grade and thickness block models covering
the entire mining or project area. The block models
form the basis from which the tonnage and grades are
reported for the various mineral resource and mineral
reserve blocks and categories. The mineral resource
categories are mainly based on the data point density.
A data point density of approximately 200m x 200m is
used for the classification of measured mineral resources.
For indicated mineral resources a density of between
200m and 400m is used. inferred mineral resources will
be classified where the density is lower than 400m x
400m. The geostatistical analysis of the exploration data
has indicated semi-variogramme ranges of at least 250m
going up to 2 000m. Geological structural characteristics
are used in addition to support the drilling density.
Other factors that are taken into consideration are regional
geology and the proximity of other operating or worked-out
mines and projects. All the non-mineralised areas,
and areas that may not be mined for various legislative or
other reasons are excluded from the mineral resources,
e.g. boundary pillars, crown pillars, large potholes,
transgressive geological bodies, fault zones, etc. The
mineral reserves are estimated by applying modifying
factors to convert the indicated mineral resources to
probable mineral reserves and the measured mineral
resources to proved mineral reserves. The following
modifying factors are used: an estimated geological loss
factor (determined by losses in mined-out areas and
projected forward), the predetermined mining extraction
rate, ore losses and ore contamination from mining
over break. The mineral reserve areas are restricted to
the five-year detailed mine plan, except in the case of
Waterval, Thorncliffe and Kroondal mines. In these cases
the LOM plans form the basis for the mineral reserves.
No inferred mineral resources have been converted to