23

INTEGRATED

ANNUAL REPORT

2017

PERFORMANCE

ABRIDGED MINERAL RESOURCES

AND MINERAL RESERVES STATEMENT

Introduction

The purpose of this report is to document the Mineral

Resources and Mineral Reserves of the Merafe Group (Merafe)

in accordance with the requirements of the South African Code

for the Reporting of Exploration Results, Mineral Resources

and Mineral Reserves, 2016 (SAMREC Code). All Merafe’s

operations are part of a pooling and sharing venture with

Glencore Operations South Africa Proprietary Limited (the

Glencore-Merafe Chrome Venture (the Venture)). Merafe has a

20.5% attributable beneficial interest in the Mineral Resources

and Mineral Reserves of the Venture. The estimates in this

document are as at 31 December 2017. To arrive at a Mineral

Resources and Mineral Reserves estimate for 31 December

2017, the budgeted production for July 2017 to December

2017 has been subtracted from the total estimates. The

Mineral Resource and Mineral Reserve information in the tables

on the following pages is based on information compiled by a

Competent Person (as defined by the SAMREC Code).

Type of mining and mining activities

The Venture has chrome mining operations along the Western

and Eastern limbs of the Bushveld Complex. The operations

along the Western Limb of the Bushveld Complex comprise

the Waterval, Kroondal and Boshoek mines. The LG6 Package

at both Waterval and Kroondal mines is mined underground

using trackless mining methods on a bord-and-pillar layout.

Boshoek Mine is 20km northwest of Rustenburg. The MG1,

LG5 and LG6 chromitite layers are the mineable open pit layers

in the Boshoek area. Boshoek Mine has been put on care and

maintenance. The Townlands Extension 9 Prospecting Right

area is an exploration project and exploration activities have been

put on hold with the Venture applying for a Retention Permit. The

eastern mining complex of the Venture consists of Thorncliffe,

Magareng and Helena mines which are situated along the

southern portion of the Eastern Limb of the Bushveld Complex.

Adjacent to these farms, the Venture has applied for a renewal

of the Prospecting Right on the farms Richmond and St George.

In addition an application has been submitted to incorporate

Richmond and St George into the eastern mines Mining Right.

The MG1 Chromitite Layer is being mined at the eastern mining

complex using underground trackless mining methods on a

bord-and-pillar mining layout.

Comparison of Mineral Resource and Mineral

Reserve estimates with previous year’s

estimates

The annual Mineral Resource and Mineral Reserve estimates

are compared with the previous year’s statement and reconciled

each year after the estimates have been finalised. Changes

in the year-on-year tonnage and grade estimates are mainly

due to mining depletion and changes in the Mineral Resource

and Mineral Reserve tonnages and grades due to additional

geological information. The biggest movement in the year on

year Mineral Resource estimate is the re-statement of the Helena

Mineral Resources and the newly stated Mineral Resources on

the St George and Richmond properties.

Material risk factors

There are no foreseen material risk factors that could affect the

validity of the current Mineral Resource and Mineral Reserve

statement. All the legislative requirements have been met with

respect to the rights to mining and prospecting for which the

Mineral Resources and Mineral Reserves have been reported.

All the operating mines are mining under new order, executed,

Mining Rights. The Prospecting Rights of all the prospecting

areas have been converted to new order Prospecting Rights.

For the complete Mineral Resources and Mineral Reserves statement

including definitions of the categorisation of mineral resources

and reserves as per the SAMREC Code 2009, descriptions and

exploration activities, geological settings of the reserves (including

maps and diagrams), legal entitlement, methods and assumptions,

material risk factors and a summary of environmental funding and

management, see our online integrated annual report for 2017.

See page 50 of the report for the Directors report and for the

statement on mining rights and mining operations.

23

INTEGRATED ANNUAL REPORT 2017